RIL's pipelines to ferry gas from KG basin: Details

Following are the details of the pipelines laid or to be laid by Reliance Gas Transport and Infrastructure Limited (RGTIL), for transporting gas from the KG basin. 

They are:

8The Kakinada-Hyderabad-Ahmedabad pipeline: This pipeline is 1,385-km long and has already been commissioned.

8The Kakinanda-Chennai pipeline: This 600 km-long pipeline is to be commissioned by the second quarter of 2012.

8The Kakinada-Basudebpur-Howrah pipeline: The length of the pipeline is proposed at 1,100 km. The pipeline is likely to be commissioned by the third quarter of 2012.

8The Chennai-Tuticorin pipeline: This pipeline is expected to be 670 km in length and is to be commissioned by the third quarter of 2012.

8The Chennai-Bangalore-Mangalore pipeline: This proposed pipeline is 660 km long and is expected to be commissioned by the third quarter of 2012. 

Source: www.indianpetro.com