December 18, 2009
NTPC not to suffer Rs 30,000 cr loss: Govt
December 3, 2009
Gas row: Govt says NTPC deal not the same as pvt accord
The apex court had sought the response after Anil Ambani-led RNRL had consented to Government being made a party in the dispute. RNRL contended that it was entitled to receive the gas at $2.34 per unit from Mukesh Ambani group RIL which had entered into an arrangement for supplying gas to NTPC at that rate.
"The rights and obligation of NTPC and RIL cannot be regarded as similar in status to the private arrangement as in the case of RIL and RNRL because NTPC is not only a PSU but the process involved for price determination in the case of NTPC gas was by international competitive bidding," the government said in the affidavit.
However, the government said the price offered by the contractor to the NTPC will require scrutiny and approval of the government under the Production Sharing contract (PSC).
"The central government will take an appropriate decision in the case of NTPC as and when a need arises. Such a decision based on public interest, if in favour of NTPC cannot be termed as discriminatory or arbitrary," the affidavit placed before a bench headed by K G Balakrishnan said.
The government said that a decision in respect of NTPC will be taken when either its rights gets established in the pending suit with RIL in the Bombay High Court or if overriding public interest warrants any government intervention.
The decision taken by EGoM at its meeting held on September 12, 2007, May 28 and October 23, 2008 additionally reflects that it has not excluded the entitlement of NTPC for consideration.
"It may be pointed out that since there exists an ongoing suit between NTPC and RIL the decisions of the central government were stated to be without prejudice to the rights of NTPC," the affidavit said.
It said any request of NTPC for supply of gas will be considered by the government in the light of the relevant provisions of the Production Sharing Contract (PSC).
Further, the affidavit said the government has on the one hand left NTPC to establish its right in the pending suit in the High Court, and on the other hand it has not foreclosed any options available under PSC.
However, such a decision would be taken by a competent authority keeping in view the character of the PSU and other relevant circumstances having a bearing on public interest.
The government clarified that the affidavit filed on January 13, 2009 before the High court was not intended to convey that government has rejected the case of NTPC or that it has chosen to signify any implied termination of the PSU's rights.
The Ambani brothers are engaged in a high-voltage bitter legal battle over the supply and price of the gas from KG Basin.
While RNRL is seeking gas at a committed price of $2.34 per unit, RIL says it cannot honour the commitment made in the family agreement due to government's pricing and gas policy.
September 24, 2009
NTPC signs pact with RIL for buying part of K-G D6 gas for $4.20
natural gas allocated to it from K-G D6 fields at a rate of USD 4.2 per mmBtu. NTPC will buy 0.61 million metric standard cubic meters of gas a day for its plant in Anta in Rajasthan, an industry official said. The gas will start flowing in the next 7-10 days, the official added.
The volumes are less than one-fourth of the 2.67 mmscmd gas the Government had allocated to NTPC.
The state-run power utility signed a Gas Sales and Purchase Agreement (GSPA) with RIL and a separate Gas Transportation Agreement with Reliance Gas Transportation Infrastructure Ltd.
The government had last year allocated 2.67 million cubic metres per day of K-G D6 gas to NTPC's Kawas and Gandhar in Gujarat and Anta power plants in Rajasthan
NTPC does not want to take RIL gas for Kawas and Gandhar plants because of the pending legal dispute over supply of gas at USD 2.34 per mmBtu price quoted by RIL in a 2004 tender. "Against an allocation of 2.67 mmscmd, GSPA for only 0.61 mmscmd of gas for Anta unit will be signed for now," he said.
"Government will have to take a call on reallocating the remaining gas to NTPC's other plants."
NTPC, which unlike the 40-odd other customers of K-G D6 gas was initially opposed to paying USD 0.135 per mmBtu marketing margin to RIL, has agreed to pay the levy.
RIL can produce over 60 mmscmd of gas from K-G D6 fields but is restricting output to 37 mmscmd in the absence of offtake from existing customers like NTPC and failure of the government to name consumers beyond the initial 40 mmscmd.
Source: http://economictimes.indiatimes.com
_____________________________________________________________________________
September 23, 2009
NTPC may sign deal with RIL for natural gas at $4.20/mmBtu
September 22, 2009
No justification for NTPC’s Rs 32K cr savings talk: RIL
September 11, 2009
What Price, Gas?

If Anil wins, the government’s power, fertiliser and city supply plans could be starved of gas.
t’s a national resource that is in danger of being cornered by two individuals—at the expense of the nation. The Ambani brothers are squabbling over the quantity and price at which Mukesh is supposed to supply gas from Reliance Industries’ (RIL’s) D-6 field in the K-G Basin to Anil. The focus of that battle has now shifted to the Supreme Court with RIL filing a writ petition on july4. But the contentious agreement between them also contains clauses that effectively divide the entire gas between the brothers. If that happens, it will make a mockery of a government policy that earmarked about half of the D-6 gas for other players and projects of national importance.
At full capacity, Reliance Industries’ daily output from the K-G basin will be 80 mmscmd (million metric standard cubic metres per day). The government’s gas utilisation policy of 2007 had promised to provide 15 mmscmd of this D-6 gas to fertiliser plants, 18 mmscmd to power plants, and 5 mmscmd for city gas distribution, and 2 mmscmd for LPG. However, a Bombay High Court decision gives the memorandum of understanding (MoU) signed by the Ambanis in 2005 precedence over the production-sharing contract between RIL and the government. The ruling, if upheld, threatens to take away the government’s legitimate right over its natural resources.
If the MoU is honoured, Anil’s Reliance Natural Resources could walk away with 28 mmscmd of gas. It will get an additional 12 mmscmd if NTPC is not able to reach an understanding with RIL. That’s 40 mmscmd. And, it will get it at $2.34, well below the market rate of $4.20.
RIL, in turn, is entitled to 25 mmscmd for captive use. The remaining 15 mmscmd would be divided among the two brothers in a 60:40 ratio, with RIL getting the larger share. Nothing will be left for the government.
RIL has signed contracts with fertiliser, power and steel companies, and begun supplying them the D-6 gas. The worry is that the MoU will put an end to this supply, forcing the plants to go back to more expensive liquid fuels such as naphtha and high-speed diesel. In turn, this would require higher subsidies and widen the budget deficit. Further, a recent Citigroup report points out: “If the issue lingers, it could discourage the emergence of demand from new power and fertiliser plants.’’
Ultimately, this could snowball into a massive legal battle. On June 24, Fertiliser Secretary Atul Chaturvedi sent a note to RS Pandey, his counterpart in the Petroleum Ministry. It stated: “If the rights of fertiliser companies are altered to their disadvantage, then the Fertiliser Association of India will be forced to seek legal remedies independently.’’ It is only a matter of time before the power and steel sectors join the raging battle.
Worse, the High Court order will hit the government hard financially. Total recoverable reserves from the D-6 field have been put at 11 trillion cubic feet (as calculated by the Directorate General of Hydrocarbons). The total revenue generated from these reserves at $4.2 per mmbtu will amount to $47.17 billion. The government’s share of these revenues will amount to $19.68 billion in the initial 15 years. But, if 40 mmscmd is sold to Anil at $2.34 per mmbtu, while the rest is sold at $4.2 per mmbtu, the government will get $10.72 billion—about $9 billion less. The biggest losers, of course, will be the people of India.
Source: Business Outlook
________________________________________________________________________________________
September 9, 2009
Regasified LNG purchase to burden electricity boards: RIL
Reliance has already written a letter addressed to the Gujarat government’s Principal Secretary (Energy and Petrochemicals) S Jagadeesan, who is also the chairman of Gujarat Urja Vikas Nigam Ltd (GUVNL) — the apex electricity company of the state. The company conveyed to the Gujarat government that NTPC’s decision to forego KG-D6 gas and purchase 6 mmscmd of RLNG could potentially increase NTPC’s cost of power by Rs 1,500 crore per annum, or Rs 15,000 crore in 10 years. At present, NTPC buys RLNG on spot basis and has contracted to buy RLNG on a term basis for 10 years.
Source: B.S
_____________________________________________________________________________________
September 7, 2009
KGD6 gas price fair and competitve says PMS Prasad

RIL Director PMS Prasad addresses the many charges laid at the company’s door.
Reliance Industries’ gas field off India’s east cost has been a subject of massive controversy for several months, with allegations of costs being inflated, and the government thereby being denied its fair share of revenue. There are allegations of price gouging, and of Reliance reneging on lower price contracts. There are charges that so-called independent experts are not independent, and that a friendly minister is favouring the company.
Some of the issues are in court, others are not. The litigants are Reliance Industries Ltd (RIL), managed by Mukesh Ambani, Reliance Natural Resources Ltd (managed by Anil Ambani) and the government-owned National Thermal Power Corporation (NTPC).
Other than speaking through court documents, Reliance Industries has so far maintained a studied silence on most of the issues raised. Now, for the first time, a senior Reliance official has spoken to a newspaper, and addressed the key points of the controversy.
In an extended interview that lasted more than two hours, PMS Prasad, who has headed RIL’s petroleum business for many years and who recently joined the company’s board, defends the company’s position and seeks to put the controversies to rest, while steering clear of all matters that he felt were sub judice.
Prasad contends that the gas price of $4.20 per million British thermal unit is fair, and in any case lower than what is being paid by companies in other deals. He also argues that Reliance’s capital cost for developing the D6 gas field compares very favourably with other such fields.
He says Reliance offered a fair deal to NTPC which, however, did not accept it and went to court; he feels NTPC is the loser, because it is buying more expensive gas from elsewhere.
He also denies the charge that Reliance has stalled any audit of its costs by the Comptroller and Auditor General, arguing that there was no contact with CAG till April this year.
Prasad feels Reliance has not got the credit it deserves for having improved the country’s energy security by producing so much gas, in such quick time, from a field where others have failed to find gas.
Excerpts from the interview:
Please respond to the charge that a gas price of $4.20 per million British thermal units (mBtu) is high, since current gas prices are at a seven-year low.
There is always a difference between contract and spot prices. Contract prices were still in $6-7 range, when spot prices went through the roof. We all know that spot LNG (liquefied natural gas) was coming to India in the $22-25 range, and we know of some deals which were done at spot prices of $27. Some contract prices are linked to the price of oil, but there too the indexation is not 100 per cent.
When this price of $4.20 was approved, spot prices were much higher at $6-8. I don’t think these comparisons (with today’s spot prices) are fair. I genuinely believe the $4.20 price, compared to other gas prices in India on spot or contract LNG price coming to India, is very competitive.
Your capital expenditure for developing the D6 field started at $2.5 billion, then became $5 billion and then $8.8 billion. This has led to charges of gold-plating and denial of revenue to the government. How do you explain such sharp increases in capital cost?
In October 2002, we announced the gas discovery and in September-October 2003, because we put in the bid to supply gas to NTPC, we wanted to see if we could develop the field as quickly as possible. We put together some concepts at the prices that were prevailing, and it would cost about $2.5 billion for initial development.
We continued to drill more wells, and do geotechnical investigations. We now knew that the reserves had gone up from the original 5 trillion cubic feet (tcf) of gas reserves that we thought were there, to 10-11 tcf. So we had to rework the original concepts. Also in 2005, we had the tsunami, so we had to do tsunami-proofing.
Prices, too, had gone up. I’ll give you an example. In 2003, we were using the rig that helped us to discover this field, and the cost we were paying was about $110,000-115,000 per day. Add the service and it was of the order of $225,000-$250,000. For the same rig today, I am paying close to $800,000 a day. The rig that we hired in 2005 and 2006, we are paying over a million dollars. That explains the increase.
We were at the peak of the commodity cycle between 2006 and 2008. Most of our commitments were made in 2006. That is the time we went to the director-general of hydrocarbons, to say that we have bigger gas reserves here. The government said you go and produce more. So we scaled up our production plan from 40 mscmd to 80 mscmd (million standard cubic metres per day).
Meanwhile, with higher crude and gas prices, everybody in the industry was investing. What otherwise was a marginal field suddenly became a viable field. But service capacity did not go up proportionately, so there was a lot of pressure on the cost of these services. That’s how our cost went up to $5.5 billion.
That was for the initial investment. When we went with the revised development plan, we did not project the cost over the life of the field, because we already had the bad experience of having estimated a cost in 2003 prices, and then revising it at 2006 prices. But the government wanted to see what will be the cost through the full life of the field, and we were asked to cost the whole thing. That is how the figure of $8.8 billion came. There is a misconception that we have spent $8.8 billion; we have not spent it. It is the money that we will be spending over the life of the field.
At $8.8 billion, what is the capital cost per unit of gas? And how does it compare internationally?
If you take 11 tcf as the reserves, it converts to 1.8 billion barrels of oil equivalent. I will spend $8.8 billion, plus the $700 million spent initially on exploration and appraisal. The total will be $9.5 billion, which works out to a little over $5 per barrel of oil equivalent. The international benchmarks are $6-9 for comparable fields.
I cannot compare our cost to anything here in India, since ONGC is yet to produce from the KG basin. Internationally, you have three ways of comparison. You can compare it to the CERA (Cambridge Energy Research Associates) cost. Then there is Goldman Sachs and another investment bank; they do cost comparisons every year in terms of reserves and development and production costs. The third is what has been announced for an international company’s project. Using these three methodologies, I think we compare very favourably.
Goldman Sachs’ benchmarking tells us that in the deepwater regime, we are among the lowest, in terms of capital cost in dollars per barrel of oil equivalent. This is also the fastest discovery and development of a field, especially when there are no support services nearby, everything has to come from Singapore or Dubai. We are among the best among comparable fields, in terms of both cost and time.
It is said that the prices of services and rigs have fallen now.
Yes, some prices have come down but not for deepwater services, which is what we need. Deepwater rig prices are exactly the same as they were in 2008, when they were at their peak. Maybe there has been a slight softening. When ONGC opened a bid for a deepwater rig in April or May, they had only two offers and one of the offers was based on the rig we were using, because that contract will be running out in one or one-and-a-half years. If you look at what is called the effective cost per day, it is $560,000-630,000. If we include associated services, it goes to over $1 million today. We are spending a million dollars a day because most of our equipment, commodity, services and deepwater installations were contracted in 2006, when the market was at its peak.
Today, the market may have come off a little but only in some senses, like jack-up rigs have fallen. But we do not use jack-up rigs or shallow water floaters. We are unfortunately drilling 1,000-1,500 metres, so we need ultra-deepwater rigs. Some of our wel
ls, which we will be drilling soon, will be at 3,000 metre. If you want to get a good price, you have to contract for a long period of, say, two, three or five years. Contractors don’t want to give a rig for a short period. Ultimately, there are only a few players in the deepwater drilling business. The BPs and the Exxons and everybody did the same thing. They signed five-, seven- or 10-year contracts at high prices. But the market did not come off. Quite a few deepwater rigs were being built but, in this economic crisis, all finances had gone and all rig construction has stopped. So in reality the rigs that were to be built are not there, and the market is still strong.
The second thing is Petrobras, with their big discovery off the coast of Brazil, requires some 38 rigs for exploring and developing fields. So, big demand is anticipated, and the market remains firm. Today, if you see the earnings of most of the exploration and production companies, they are not great because they are still paying high costs, while the prices of oil and gas are not great.
If you are so confident about your costs, why have you stalled for two years the audit of your costs by the CAG (Comptroller and Auditor General)?
I am very surprised to hear this. We have had only one interaction with CAG — that was in April-May this year, when there was a meeting in the ministry to which eight operators were invited and the government said CAG will audit contractors. This question of stalling for two years has come absolutely out of the blue. I must correct myself, there was a more recent interaction in August, which was a meeting specific for D6. We stated our contractual position. We said you are welcome to do the audit but the government has already appointed an auditor to do it till 2006-07, and our agreement provides for only one audit. So, why doesn’t CAG start auditing on a prospective basis? That was a suggestion we made. But after the meeting, we talked it over. We have nothing to hide. So, even though it is outside the scope of PSC, we have said we welcome the CAG audit and the scope of it.
If your first contact with CAG was in April, and they say you have been stalling it for two years, did you take this up with CAG?
No, because we have received only one letter from CAG inviting us for the meeting. They never asked for any specific records. There is no question of stalling CAG. Now a new date is being discussed some time in the third or fourth week of September to sit with CAG and the petroleum ministry to agree on the methodology. Anything on which the government has a right under the production sharing contract (PSC), there is absolutely no question of stalling it. We will cooperate. If it is beyond PSC, if it is a question of showing how transparent we are, we won’t mind considering even that.
Do you make money at a gas price of $2.34 per mBtu (the price offered to NTPC)?
What happens under the PSC is that the contractor recovers his investment first and then the government share goes up. Ten tcf of gas is 10 billion million Btu. You multiply that by $2.34, and you get total revenue from the field of $23.4 billion. I have to recover all my costs, which are $9.5 billion. Government profit starts after that, and climbs progressively from 10 per cent and goes up to 80 per cent. If there is less revenue because of a lower price, it is government profit that gets impacted most, while I recover my cost over a longer period. If the price is $4.20, the total revenue goes up to $42 billion, and the government’s profit share goes up. My cost is fixed.
So, both you and the government have a stake in a higher price, except that the government also pays a higher subsidy on the end products of the user industries, which are fertiliser and power.
Yes and no. It depends on what we compare with. We end up comparing with the administered price mechanism. Typically, natural gas equals the crude oil price, divided by 10 or 15. In a depressed market, it will be 15. In a bullish market, it may be 10 or even less. When we bid for NTPC, oil prices were $27 and we looked at the forward curve. After we recover costs, we do make money but it takes me longer to recover costs, and time is money. If NTPC had signed the contract in December 2005, we would have submitted the contract to the government. If approved, we could have been supplying at $2.34.
The NTPC-RIL gas dispute was over limiting liabilities at a time when production from the D6 field had not started. Now, when you have started production, what is the dispute?
Our disagreement with NTPC was not on price, tenure or the quantity of gas — none of the factors that would in any way negatively affect the economic value of the contract for NTPC. Once we were seen to be the lowest bidder, NTPC and we engaged in extended discussion on various contract issues for more than a year. The main outstanding issue was about liabilities in case of failure to supply, which we felt had to be limited because we were not going to bet the entire company for the sake of a single contract. We offered 50 per cent higher liabilities than what NTPC was giving us for non-acceptance of delivery of gas. We also said that if we produced any gas at all, the first gas up to the contracted amount would go to NTPC. What more could they have asked for?
In no other contract has NTPC got unlimited liabilities of the kind they wanted from us. Our bona fides were shown when we actually signed the agreement incorporating all the agreed clauses and a few other clauses where we had disagreement but where we thought we were right. The main outstanding issue was the extent of liabilities in case of failure to supply gas.
NTPC was silent towards the end, and then reverted to their position at the start of the entire exercise, thus wiping out all the subsequent discussions. Then the company went to court. At that stage, we had no option but to say that since you have not accepted what we signed, and have gone to court, we are withdrawing our offer.
We argue that there was no completed contract because NTPC did not sign. If the court determines that there is a concluded contract between NTPC and Reliance, then we would definitely sign the contract but we would still have an issue with unlimited liabilities. We will also go to the government for approval of the price, according to the provision in the production sharing contract. This is our position today.
So, is NTPC the loser by not signing the contract you sent them and going to court instead?
I would think so. When the economic value of the contract is protected and a reasonable date of supply is known, liabilities are important but they cannot make or break the contract. They have been buying gas at much higher prices from elsewhere.
There is a perception that at $4.20, the price formula is structured in such a way that if global prices fall, you are protected on your revenues. But if they rise, you gain, and therefore it is an asymmetrical structure. Is it right that you are de-risked in this way?
We get a base price of $2.50 if the crude price falls to $25. Our price changes when crude varies between $25 and $60, at which stage it is capped. The gas price is capped at $4.20. There is a floor and a cap. Yes, it is de-risked, but remember that the contractor has taken the risk of exploration and put big money there.
When you come to market-based prices, right in shallow waters in the KG basin, gas is being sold at $4.30 which is due for revision; and on the west coast, the price range is $4.50-5.70. These are domestic prices and non-administered prices. It is a market-based price and has no relation to the cost. There is the question as to why should it be linked to the international price. But then nobody asks why is Bombay High oil sold by ONGC linked to Brent, or why Panna-Mukta-Tapti or Ravva crude oil is linked to the international price.
The allegation is that at $4.20, you are not able to sell gas, because prices are lower elsewhere, which is why you are not meeting the production target.
If the government frees me to sell the gas, or alternatively establish a mechanism to give a list of customers, I can guarantee you the balance of 30-40 mscmd that we are ready to produce, we can contract immediately. I need 15 mscmd for my own captive plants. That’s what we have requested the government.
The narrative that has been put out is that you have raised sharply your capex cost, you have thereby reduced the government’s share of revenue, you have a gas price fixed in your favour, and you have a friendly minister. And you are taking a natural resource, where the cost of fertiliser and power depends on the price you get, and you are not allowing your cost to be audited, and your so-called independent experts are not independent at all. This is the picture that has gained currency, which seems to be completely at odds with what you are saying.
We are totally transparent and welcome any audit as long as it is within the borders of the PSC. Somebody’s image and reputation has been tarnished. We didn’t know Mustang [one of the independent experts]. We never considered buying them. We are in the business of plants and assets, we do not want to buy engineering companies. About Mustang saying that it was awarded a multi-million contract after this is not correct. Everybody knows in Panna Mukta Tapti, it is British Gas that is the operator. We are only a 30 per cent partner and BG is awarding contracts on the basis of competitive bids. It is bad to tarnish people’s reputation.
As regards the other expert, Gopalakrishnan. I met him only once when he came to audit. I did not know him. He worked for many years in ONGC and went to Kuwait Oil. He had a good reputation as a reservoir engineer. If after that or before, he is a visiting faculty in Deendayal Institute of Petroleum where Mukesh Ambani is honorary chairman, I do not think they ever met. If you put such linkages, and rubbish people’s reputation, you won’t find anybody. There are four or five people in this space. They might have worked somewhere or the other. It is not fair to criticise people. Does CAG have an industry expert? For that, they will need to get somebody.
You did not address the point on having a friendly minister.
I do not know. Ultimately, the government does what is good for it. You have Murli Deora as the honourable minister of petroleum and natural gas. I am sure he is known to the (Ambani) family and both the brothers equally. A friendly minister does not mean that he is going to favour us. If that is the perception, I would wish that there was a different minister, because this perception would not have been there and things would have moved faster. Today, because of this, you have put the minister on the defensive.
The government has tied itself in knots by saying different things at different points of time. That is why there is a credibility issue, and the minister becomes relevant.
This is a path-breaking exercise, and the government is also interpreting as it goes along. We are the first. We ourselves did not understand what some things meant. We did not know what price approval meant. We thought a gas utilisation policy was something in broad terms. We did not know that it was not only sectoral priorities but constraints on our marketing freedom and also that they can allocate customers in each segment by volume and then say you cannot give more or less.
Clarity came through the formation of EGoM and the government made decisions subsequently. Before that, we did not get any approval (from the minister). Price approval, utilisation and allocation came from EGoM. The development plan is approved by a management committee that has representatives of operators and government, and both government representatives have to sign on before we can get the green signal. The assets and resources belong to the government, the risks are of the contractor.
RIL says now that gas is a sovereign property and it is not the owner of the gas. Did Mukesh Ambani not know this at the time of signing the family MoU?
We signed the family MoU, thinking government approval will come later. We did not know the process and the utilisation policy. The PSC did cover issues but what the contours would be, we did not know. The MoU says both the groups will try to get government approval. When you do not know, you try to take risks but you hedge it.
Source:B.S
_____________________________________________________________________________________
NTPC vs RIL updates on KGD6 gas
September 4, 2009
RIL says it signed gas contract, only NTPC did not
September 3, 2009
RIL blames NTPC for not signing gas purchase pact
Reliance Industries (RIL) has complained to Power Ministry about NTPC's reluctance to sign an agreement to buy gas from it and said that the power PSU stands to lose Rs 15,000 crore if it imports LNG. The government had allocated 2.67 million standard cubic meters per day (mmscmd) of gas from RIL's eastern offshore KG-D6 fields to NTPC, but unlike the 35 other customers identified for the gas, the state-run firm is yet to sign a Gas Sales and Purchase Agreement (GSPA).
Mr Prasad, in the letter, has emphatically stated that much against the publicised campaign regarding NTPC’s losses, the company will remain unaffected by any change in the gas price. The Anil Ambani group had alleged that the state power utility will lose around Rs 30,000 crore due to the hike in gas prices. “The difference in fuel price between $4.2/unit and $2.34/unit results in an increase of power costs by not more than 60 paise/unit. NTPC remains unaffected because the cost of fuel is passed on to state electricity boards,” the letter said.
Mr Prasad has also questioned NTPC’s 10-year contract for RLNG, which, he insists, will cost the company much more than KG D6 gas. “At an assumed price of $60/bbl for crude oil, the average delivered price for this RLNG is at $11.2/mmbtu. On the other hand, the KG D6 gas as per $4.2/mmbtu will result in a delivered price of $6.5/mmbtu,”
RIL's KG-D6 fields can today produce more than 60 mmscmd but the company is forced to cap output at 36-37 mmscmd as customers like NTPC have not started taking their quota.
"In our last meeting with NTPC on August 12, all issues relating to finalisation of GSPA were resolved and NTPC was to revert after obtaining internal approvals. However, we are still awaiting a formal response from NTPC in spite of regular follow-up," RIL Executive Director P M S Prasad wrote to Power Secretary H S Brahma on August 31.
RIL had agreed to sign the GSPA with the caveat that the agreements would be "without prejudice" to the outcome of the case in Bombay High Court over a 2004 tender where the Mukesh Ambani firm had quoted $2.34 per mmBtu as price for gas to be supplied to NTPC's Kawas and Gandhar plants, he said.
Instead, NTPC has signed-up to buy 2.5 mmscmd of LNG for 10 years from overseas market and the delivered cost of this would be $11.2 per mmBtu as compared to KG-D6 burner tip cost of $6.5 per mmBtu, leading to a loss of Rs 600 crore per annum. Besides, NTPC buys 3-4 mmscmd LNG on spot basis, resulting in additional outgo of Rs 900 crore per annum.
RIL's KG-D6 fields can today produce more than 60 mmscmd but the company is forced to cap output at 36-37 mmscmd as customers like NTPC have not started taking their quota.
"... It is indeed strange that NTPC does not want to discuss the GSPA for the existing Kawas and Gandhar plants even through the ongoing litigation relates to the proposed expansion of Kawas and Gandhar plants. RIL, therefore, finds this stance of NTPC quite incomprehensible," Prasad wrote.
He rebutted NTPC's claims that the $4.20 per mmBtu price for KG-D6 gas (delivered price of $6.54 after adding taxes and transportation) would result in increase in cost of power, saying the difference between $4.2 per mmBtu and $2.34 per mmBtu rates "actually results in an increase in the cost of power by not more than 60 paise per unit."
"Moreover, NTPC remains unaffected by any change in price of fuel because the cost of fuel is passed on by NTPC to the state electricity boards," he wrote. "If NTPC buys gas from KG-D6, it would actually result in significant reduction in cost of power purchased by the SEBs from NTPC compared to the cost at which the SEBs are today being forced to buy power from NTPC."
The average cost of power by NTPC to SEBs in 2008-09 from its Kawas and Gandhar plants was Rs 6.34 per unit and Rs 4.64 per unit respectively, implying average cost of fuel purchased by NTPC was $16 per mmBtu and $11 per mmBtu, respectively.
Thus, the total potential increase in cost of power by NTPC’s decision to buy about 6 mscmd R-LNG instead of D6 gas, could be about Rs 1,500 crore a year, which will be borne by the State electricity boards and the consumers.
Source:ET
_____________________________________________________________________________________
Anil Ambani and Reliance : Gas production
Govt delays restricting RIL’s production: Prasad
Gas production from Reliance Industries Ltd’s (RIL) KG D6 block in the Bay of Bengal has the potential to cut India’s import bill by 20%, or nearly Rs50,000 crore. RIL is currently producing around 40 million standard cu. m per day (mscmd) and says that although it can increase production to 60 mscmd immediately, it cannot because the government has still not provided it a list of companies that will get the additional gas. Edited excerpts from an interview with executive director P.M.S. Prasad:
When are you going to hit the peak (production) of 80 mscmd?
We are ready to produce more than 60 mscmd and we are waiting for the government to give us more linkages to customers. Right now, they have given us linkages up to 40 mscmd. We have signed all agreements with NTPC. We are also almost delivering gas to people except one or two customers like Essar (Steel Ltd) and GAIL (India Ltd) who will be taking gas probably next week. Ratnagiri Gas and Power Pvt. Ltd (RGPPL), Dabhol, would start taking gas from 1 October. But otherwise we are almost there at 40 million. So, now we are eagerly waiting for the new eGoM (empowered group of ministers) to be formed so that the government can give us more linkages.
Is the government giving you a time frame? Do you lose money if you do not ramp up?
We do, a lot. The Rs35,000-36,000 crore that we have invested is Reliance’s money. It is Reliance shareholders’ money, the money that Reliance borrowed from the banks and if we are not able to earn revenues from these investments, it is a loss of present value.
One of the allegations is that you are deliberately not ramping up production, you are hoarding gas, you are artificially creating a scarcity. What are your thoughts on that?
I can only laugh because no one after having invested this much money would want to not produce. For the next five years, the gas price is fixed. So, how does it help me? Secondly, I have to repay my debt, so how does it help me not to get the revenues today. The only reason that we are not able to produce more is because of the procedural delays in forming the new eGoM and then giving us more allocations.
Because of what the government is not able to fast-track, you are not able to ramp up the capacity?
Absolutely. So on a lighter note, it is the government which is hoarding the gas, not Reliance.
The other thing which has gone against you in the recent few months has been the clarification that now the seven-year income tax holiday does not stand, what does that mean for you? What kind of a hit will you take?
It is a big hit because in the production sharing contracts and also in other supporting documentation, it is very clearly mentioned that both oil and gas are eligible for tax holiday. We can give a new definition to the mineral oil just for the sake of section 80IB and then say, this doesn’t include gas. But I think it is unfair and we have been made a promise based on which we all took so much risk and then put in these big investments and then when the investments are about to fructify, saying that the gas is not entitled to a tax holiday, I think is a bit unfair.
Can you give us a broad range, what could it mean for Reliance Industries?
It would be of the order of a couple of billion dollars over seven years, but I need to re-check the numbers. You are a financial channel, so you love to have the numbers. but I hate to give out numbers because these are very sensitive information.
But if you don’t get that income- tax holiday, would you consider arbitration? What would be the next step?
Yes, arbitration is the last resort but right now the government has said that since this matter is sub judice, let the courts decide. So, we will wait for the courts to decide in some of the pending issues. But if that decision doesn’t come through, then we do have to look at other means including arbitration.
The government has arrived at a pricing valuation of $4.2 per mmBtu (million British thermal units). Is this a reasonable price? Is it a competitive price?
Yes. I genuinely think it is a very competitive price for two reasons. One, compare it with the rest of the gas that is being produced and sold in
Do you genuinely believe that the government’s revenues will be the maximum at a valuation as well as a sale price of $4.2 per mmBtu?
Higher the price, government’s stake will be higher because the contractor recovers its investment first and as the contractor recovers its investment, the government stake keeps on increasing. That is the first part.
The sooner you get profitable, the government’s share of profit petroleum increases that much sooner?
Exactly. The second part is higher the price, the quicker will be our cost recovery and then government will end up getting a higher and higher share of profits. But then government has to strike a balance between what is good for the consumers vis-à-vis what is good for the partners in the production sharing contract (PSC).
So, at $4.2 government calculations, they tend to make about Rs80,000-85,000 crore over the life of this field. I do believe those numbers.
So the government’s share at $4.2 is not the alleged Rs500 crore?
No. Rs500 crore is what they would make in the first year as royalty. So those numbers are plucked out of nowhere.
Is this figure also plucked out of nowhere—that NTPC may lose Rs30,000 crore if it is not sold gas at $2.34?
I will give you a different perspective to it. First of all, NTPC doesn’t lose anything. The reason is NTPC being a public sector undertaking (PSU), for them the fuel cost is a pass-through.
So, if they buy fuel at X dollars, that X dollars will be passed by NTPC to the state electricity boards. Today, if you take FY09 figures, NTPC’s cost of producing power from the Kawas and Gandhar plants is of the order of Rs5-6 per kilo; this is because they are using expensive fuels. If you take this KG D6 gas, that cost would come down by something like Rs2-3 per kilo.
So, how can you put an argument that they are going to lose Rs30,000 crore? It’s the other way round. By not buying our gas NTPC is losing money.
Source:HBL
___________________________________________________________________________________
